Summary of Proposal Package
· $20.9 million in OUS base budget (core proposals)
· $22.1 million in Policy Package (new initiative proposals)
·
$18.2 million in
OUS Capital Investment
- tier one: priority 7 (projects considered to be completing existing
assets)
- tier two: priority 27 (projects considered new)
OSBHE approves budget submission, July 2004 press release
Presentation to OSBHE (July 2004)
Policy Package Proposal submitted to OSBHE April 23, 2004
Recommended Allocations approved at April 23, 2004 ETIC meeting
Metrics Analysis of Core Proposals (April 22, 2004)
Financial Summary of all proposals received (updated April 22, 2004)
Revisions/Additions
since April 9th Voting Member's Meeting
(links in table
below have been updated)
2. EOU Biotech New Initiative - revised
4. OGI and PSU Biomedical Engineering Statement
5. OGI and EOU Biomedical Engineering Statement
6. OGI Core Proposal (marked version)
7. OGI New Initiative - revised
8. OSU New Initiative I - amended (marked version)
9. OSU New Initiative II - amended and reduced amount
10. PSU Core Proposal (marked version)
11. UO New Initiative CSIT - revised (marked) and Statement
12. UO Response to CIS Metrics questions
April 9th ETIC Voting
Member Meeting
Worksheet for scoring proposals (updated April 8, 2004)
|
2005-2007 Campus Requests ($M) Updated April 22, 2004 |
|||||
|
University |
Core |
New Initiatives |
Capital |
Total Request |
Private Support |
|
EOU |
Summary |
$1.50 |
$1.25 |
||
|
OHSU/OGI |
$4.80 |
$7.80 |
|||
|
OIT |
$3.14 |
$2.94 |
|||
|
OSU |
$20.83 |
$36.01 |
|||
|
PSU |
5.41 |
1.0 Biomedical |
$19.25 |
$32.35 |
|
|
SOU |
n/a |
n/a |
$0.53 |
$0.27 |
|
|
UO |
$9.17 |
$16.46 |
|||
|
WOU |
n/a |
$0.45 |
$0.23 |
||
|
Total |
$21.36 |
$24.46 |
$13.85 |
$59.67 |
$97.30 |
|
PreCollege |
n/a |
$1.51 |
|
||
|
(1) PreCollege request included in host university requests. EOU's PreCollege new initiative not included in the collaborative proposal. |
|||||
Proposal Timeline
4/02/04 - proposals
due
4/05/04 - rollup of proposals distributed to ETIC members
4/09/04 - ETIC voting members meet and review proposals
4/10/04 - requests for changes/clarifications to campuses
4/13/04 - requested revisions submitted
4/15/04 - ETIC voting members produce overall proposal
4/23/04 - ETIC meeting for review and approval of proposal for Board submission
5/06/04 - OSBHE meeting
Request for Proposals (March 24, 2004)
New
Initiative Proposal template
Capital
Investment Proposal template